Over Weekend 21 we had a team out supporting the installation of trash screens at London Charing Cross working alongside dozens of other teams supporting the final stages of the refurbishment of the platforms at Charing Cross in this 27-hour possession.
Our team of 8 were assisting with the cutting and installation of trash screens underneath the platforms 4-6. With various other teams completing similar works across other platforms, we completed our sections in good time for the hand back.
It was great to be involved, albeit in a small way, on the refurbishment of Charing Cross, a project that saw the station closed for 22 days whilst major upgrades were undertaken.
Supporting our client Volker FitzPatrick and SRE, it was great to be involved, albeit in a small way, on the refurbishment of Charing Cross, a project that saw the station closed for 22 days whilst major upgrades were undertaken earlier in the month.